Planned route: 4 segments · ~2 days steaming · 3 stations

Operating area: Cascadia Margin and

Route: Newport (Oregon) - United States → Newport (Oregon) - United States


Aug 18 – Aug 23, 20254 days at seaactual: departed Aug 18, 2025, arrived Aug 23, 2025

Open the fleet timeline


Project aboard

We are requesting use of the R/V Sally Ride to recover and install three Deep Profiler Moorings as part of the annual Operations and Maintenance cruise for the National Science Foundations Ocean Observatories Initiative Regional Cabled Array. This work was postponed in 2024 due because the moorings could not be turned on the R/V Atlantis . This will require a two-ship operation utilizing the Sally Ride for the mooring turns and the Atlantis with Jason to unplug and plug in the moorings.


People aboard

  • Deborah Kelley · Principal investigator

Party size: 12

Estimated vacant berths: 14

Equipment

Aboard the vessel

  • Ship Fitted Winches & Wires
  • Crane
  • Stern A-Frame
  • Navigation - Heading/Position
  • Dynamic Positioning (DP)
  • Pinger, 12kHz
  • ADCP/UHDAS – range 250-350m (e.g. 150kHz)

Science party brings

  • Science Supplied Portable Winch

Schedule data from UNOLS Marine Facilities Planning · operator cruise code SR2518 Michel-Hart · MFP reference 24/4673 · synced Sep 24, 2026