VesselConnect

MD RTMM ES 2025

Completed
Pelican

Pelican

Louisiana Universities Marine Consortium · USA

Loading map…
PortPlanned routeMooring / vehicle

Planned route: 2 segments · ~25 hours steaming · 1 station

Operating area: US GoM, Approx. 120 nm S of Cocodrie, LA

Route: Cocodrie (Louisiana) - United States → Cocodrie (Louisiana) - United States


Feb 1 – Feb 5, 20254 days at seaactual: departed Feb 1, 2025, arrived Feb 5, 2025

Open the fleet timeline


Project aboard

Our real time metocean buoy has a power failure in the main battery bank of the surface buoy. We intend to recover the surface buoy, repair the power issue, and then redeploy the surface buoy. We do not intend on recovering the entirety of the mooring, just the surface buoy. Temporary flotation will be deployed in place of the surface buoy to prevent us from having to recover the main mooring line and components.


People aboard

  • Eric Aronchick · Principal investigator

Party size: 4

Estimated vacant berths: 12

Equipment

Aboard the vessel

  • Ship Fitted Winches & Wires
  • Crane
  • Stern A-Frame
  • Meteorological Data
  • ADCP/UHDAS – range < 30m (e.g. 600kHz-1200kHz)
  • ADCP/UHDAS – range < 80m (eg. 300kHz)
  • ADCP/UHDAS – range 500-750m (e.g. 75kHz)

Schedule data from UNOLS Marine Facilities Planning · operator cruise code WHG · MFP reference 25/5609 · synced Sep 24, 2026